Start: | June 8, 2007 |
Finish: | July 3, 2007 |
Phase: | Phase 1 |
Report Date: | June 16, 2007 |
|
|
WBS | Name | Start | Finish | Work | Priority | Complete | Cost |
---|---|---|---|---|---|---|---|
1 | Implement KeyBoard Support | Jun 8 | Jun 17 | 13d 2h | |||
1.1 | Retrive specific item groups | Jun 8 | Jun 9 | 1d 2h | 100% | ||
1.2 | Implement a logic to navigate through items | Jun 9 | Jun 10 | 2d | 100% | ||
1.3 | Design and Testing | Jun 10 | Jun 12 | 3d | 100% | ||
1.4 | KeyBord Support Implemented | Jun 12 | Jun 12 | ||||
1.5 | Bug fixing | Jun 12 | Jun 13 | 2d | 50% | ||
1.6 | Add additional key events | Jun 13 | Jun 17 | 5d | 40% | ||
2 | TOM | Jun 17 | Jul 3 | 31d | |||
2.1 | Design a model architecture | Jun 17 | Jun 24 | 8d | 0% | ||
2.2 | Build the design | Jun 19 | Jul 3 | 23d | |||
2.2.1 | Implement the base classes | Jun 19 | Jun 28 | 10d | 0% | ||
2.2.2 | Finish the core part | Jun 28 | Jun 28 | ||||
2.2.3 | Developing with XMLs | Jun 24 | Jun 30 | 7d | 0% | ||
2.2.4 | Design the UI | Jun 27 | Jul 2 | 6d | 0% | ||
2.2.5 | End of Phase-1 | Jul 3 | Jul 3 |
Name | Short name | Type | Group | Cost | |
---|---|---|---|---|---|
Lahiru Lakmal Priyadarshana | Lahiru | Work | address@hidden | 0 |
patch-15-06-2007.tar
Description: Unix tar archive