Hi!
Andy Wingo <address@hidden> writes:
> Yes. We probably would need the longer freeze (of 10 days) to get the
> docs and NEWS and things in shape for this one, meaning no new code
> should go in between the 5th and the 15th, just testing and doc updates
> and regression fixes. Sound good to you?
Yes, but... it just occurred to me that I'll be away from the 2nd to
the 18th of June, so I probably won't commit new code, but I won't be
available either to make the actual release. Unless we wait for a few
more days for this one.