Re: 1.9.1 checklist
From: |
Mike Gran |
Subject: |
Re: 1.9.1 checklist |
Date: |
Tue, 26 May 2009 15:37:46 -0700 (PDT) |
> Hey folks!
>
> So, IMO we need to start pushing towards a release. How about getting a
> 1.9.1 out soon?
>
> Unicode:
> Code shaping up, needs review and R6RS-libs. Unclear how much will be
> in shape for 2.0. Acceptable to ship with only the finished parts.
>
The big steps to hit a beta on Unicode are transcoders in R6RS I/O,
charsets that have more than 256 characters, some serious profiling,
and unicode-sized characters and strings in the virtual machine,
compiler, and REPL. Also readline may need some work.
> Basically at this point the features are coming together, and we need
> testing and exposure to focus the hackpower on what's important.
>
> My proposal would be a time-based release schedule. We can decide the
> Guile 2.0 release date now, and three or four micro releases before
> then.
FWIW, I think the most imporant attribute of a 2.0 release is that it
doesn't break the code by Guile's four big customers: Gnucash,
GCC via Autogen,SND, and Lilypond.
-Mike Gran