Sebastjan Trepca <trepca <at> gmail.com> writes:
> I was wondering if there is a way to set a time estimate for a task
> and then match it with actual logged time? After you finish it of
> course.
>
> Maybe something similar as checkbox counters.
>
> * TODO learn about emacs [0/2, 0h/20h]
> - [ ] read emacs manual (10h)
> - [ ] read elisp manual (10h)
>
> First counter counts the finished subtasks, second shows overall
> logged time and the estimate.
You might be able to do something with a column view. You define the effort as a
property and in your Column View you summarize the effort. Might be worth to
have a look at http://orgmode.org/org.html#Column-view